Work and Time: Bank Exam Practice Questions (SBI, IBPS, RRB, PO & Clerk)

Q. 1 12 women can complete 1/3 of a work in 8 days. How many days will 18 women take to complete the whole work?
Check Solution

Ans: D

Explanation: First, find out how much work 12 women can do in a day. They complete 1/3 of the work in 8 days, so they complete (1/3) / 8 = 1/24 of the work per day.

Next, find the daily work rate of one woman. Since 12 women do 1/24 of the work per day, one woman does (1/24) / 12 = 1/288 of the work per day.

Then, find the combined daily work rate of 18 women. 18 women do 18 * (1/288) = 1/16 of the work per day.

Finally, calculate the number of days for 18 women to complete the whole work. If they do 1/16 of the work per day, it will take them 1 / (1/16) = 16 days.

Q. 2 A can finish a task in 24 days, and B can finish the same task in 30 days. They work together for 12 days, then A quits. How many days does B need to finish the rest of the work?
Check Solution

Ans: A

Explanation: Let’s assume the total work is the Least Common Multiple (LCM) of 24 and 30, which is 120 units.

A’s work rate: 120 units / 24 days = 5 units/day
B’s work rate: 120 units / 30 days = 4 units/day
Working together for 12 days, they complete: 12 days * (5 + 4) units/day = 12 * 9 = 108 units
Remaining work: 120 units – 108 units = 12 units
B needs to finish the rest of the work.
Number of days B needs: 12 units / 4 units/day = 3 days

Correct Option: A

Q. 3 A cistern has three pipes. The first can fill it in 10 hours, the second can fill it in 12 hours, and the third can empty it in 20 hours. If all three pipes are opened simultaneously, how long will it take to fill the cistern?
Check Solution

Ans: B

Explanation: Let the volume of the cistern be V. The filling rates of the first, second, and third pipes are V/10, V/12, and -V/20 (negative since it empties), respectively. When all three pipes are open, the net filling rate is V/10 + V/12 – V/20 = (6V + 5V – 3V) / 60 = 8V/60 = 2V/15. Let t be the time to fill the cistern when all three pipes are open. Then (2V/15) * t = V. Therefore, t = 15/2 = 7.5 hours.

Q. 4 A tailor can stitch 15 shirts in 3 days. How many shirts can the tailor stitch in 12 days?
Check Solution

Ans: A

Explanation: First, find out how many shirts the tailor stitches in one day. If the tailor stitches 15 shirts in 3 days, then in one day the tailor stitches 15/3 = 5 shirts. Now, multiply the shirts stitched in one day by the number of days given (12). So, 5 shirts/day * 12 days = 60 shirts.

Q. 5 A water tank has two pipes. The first pipe fills at a rate of 10 liters per minute and can fill the tank in 1 hour. How long will it take the second pipe, which fills at a rate of 15 liters per minute, to fill the same tank?
Check Solution

Ans: B

Explanation: First find the tank’s capacity. The first pipe fills at 10 liters/minute and fills the tank in 1 hour (60 minutes). So the tank’s capacity is 10 liters/minute * 60 minutes = 600 liters. The second pipe fills at 15 liters/minute. Time taken to fill the tank = Tank capacity / filling rate = 600 liters / 15 liters/minute = 40 minutes.

Q. 6 If 50 men and 60 women complete a task in 5 days, and 30 men and 20 women complete the same task in 9 days, how long will it take 4 men and 6 women to complete the same task?
Check Solution

Ans: C

Explanation: Let’s denote the work done by one man in one day as ‘m’ and the work done by one woman in one day as ‘w’. We can form two equations based on the given information:

Equation 1: (50m + 60w) * 5 = 1 (where 1 represents the complete task)
Equation 2: (30m + 20w) * 9 = 1

From Equation 1: 250m + 300w = 1
From Equation 2: 270m + 180w = 1

Now we need to solve these two equations to find the values of ‘m’ and ‘w’. Multiply Equation 1 by 9 and Equation 2 by 5 to eliminate the ‘1’:

New Equation 1: 2250m + 2700w = 9
New Equation 2: 1350m + 900w = 5

Multiply New Equation 2 by 3:
4050m + 2700w = 15

Subtract New Equation 1 from this modified Equation 2:
(4050m + 2700w) – (2250m + 2700w) = 15 – 9
1800m = 6
m = 6/1800 = 1/300

Substitute m = 1/300 into Equation 1:
250(1/300) + 300w = 1
5/6 + 300w = 1
300w = 1/6
w = 1/1800

Now we can determine how long it takes 4 men and 6 women to complete the task. Their combined work rate is:
4m + 6w = 4(1/300) + 6(1/1800) = 4/300 + 6/1800 = 24/1800 + 6/1800 = 30/1800 = 1/60

Time taken = 1 / (combined work rate) = 1 / (1/60) = 60 days

Correct Option: C

Q. 7 If John can paint a wall in 6 hours and Mary can paint the same wall in 3 hours, how many hours will it take them to paint the wall together?
Check Solution

Ans: E

Explanation: First, find the rate at which each person paints. John’s rate is 1/6 (one wall in 6 hours), and Mary’s rate is 1/3 (one wall in 3 hours). When they work together, their rates add up. So their combined rate is 1/6 + 1/3 = 1/6 + 2/6 = 3/6 = 1/2. This means they complete 1/2 of the wall in one hour. To find the time it takes to complete the whole wall (1 wall), take the inverse of the combined rate which is 2 hours.

Q. 8 Pipe A can fill a cistern in 12 hours. Due to a leak in the bottom, the full cistern empties in 20 hours. If the pipe is opened and the leak is also active, how long will it take to fill the cistern?
Check Solution

Ans: D

Explanation: Let the capacity of the cistern be the Least Common Multiple (LCM) of 12 and 20, which is 60 units. Pipe A fills the cistern at a rate of 60/12 = 5 units per hour. The leak empties the full cistern in 20 hours, so the leak’s rate is 60/20 = 3 units per hour (emptying). When both pipe A and the leak are active, the net filling rate is 5 – 3 = 2 units per hour. Therefore, the time taken to fill the cistern with both active is 60/2 = 30 hours.

Q. 9 Pipe A can fill a tank in 12 hours, pipe B can fill the same tank in 15 hours, and pipe C can empty the tank in 10 hours. If all three pipes are opened simultaneously when the tank is empty, how long will it take to fill the tank?
Check Solution

Ans: E

Explanation: Let’s determine the rate at which each pipe fills or empties the tank. Pipe A fills 1/12 of the tank per hour. Pipe B fills 1/15 of the tank per hour. Pipe C empties 1/10 of the tank per hour. When all three pipes are open, the combined rate is (1/12) + (1/15) – (1/10). Find a common denominator, which is 60. So the combined rate is (5/60) + (4/60) – (6/60) = 3/60 = 1/20. Since the combined rate is 1/20, it will take 20 hours to fill the tank.

Q. 10 Pipe A fills a tank in 12 hours, and pipe B fills the same tank in 15 hours. Pipe C empties the tank. If all three pipes together fill the tank in 10 hours, how long does it take pipe C to empty the full tank on its own?
Check Solution

Ans: A

Explanation: Let the volume of the tank be V.
Pipe A fills the tank in 12 hours, so its rate is V/12.
Pipe B fills the tank in 15 hours, so its rate is V/15.
Let pipe C empty the tank in x hours, so its rate is -V/x (negative because it empties).
When all three pipes work together, they fill the tank in 10 hours. So, their combined rate is V/10.
The combined rate is also the sum of the individual rates: (V/12) + (V/15) – (V/x) = V/10.
Divide the equation by V: (1/12) + (1/15) – (1/x) = 1/10.
Find a common denominator for the fractions: (5/60) + (4/60) – (1/x) = 6/60.
Combine the fractions: 9/60 – 1/x = 6/60.
Subtract 9/60 from both sides: -1/x = 6/60 – 9/60.
-1/x = -3/60.
-1/x = -1/20.
Therefore, x = 20.

Correct Option: A

Q. 11 Pipe C takes 1.5 times longer than pipe A to fill a tank individually. Pipes B and C have a time ratio of 4:5 to fill the tank alone. All three pipes together fill the tank in 4 minutes. If the pipes operate in turns (A, then B, then C) for 5-minute intervals, starting with pipe A, how long will it take to fill the tank?
Check Solution

Ans: E

Explanation:
Let the time taken by Pipe A to fill the tank be ‘a’ minutes.
Pipe C takes 1.5 times longer than pipe A, so Pipe C takes 1.5a minutes to fill the tank.
Let the time taken by Pipe B to fill the tank be ‘b’ minutes.
The time ratio for B and C is 4:5, so b / (1.5a) = 4/5. Therefore, b = (4/5) * 1.5a = 1.2a.
The work done by the pipes in one minute is:
Pipe A: 1/a
Pipe B: 1/1.2a = 5/6a
Pipe C: 1/1.5a = 2/3a
All three pipes together fill the tank in 4 minutes, so their combined work in one minute is 1/4.
Therefore, (1/a) + (5/6a) + (2/3a) = 1/4
Multiplying by 12a gives: 12 + 10 + 8 = 3a => 30 = 3a => a = 10 minutes.
So, A takes 10 mins, B takes 1.2*10 = 12 minutes, and C takes 1.5*10 = 15 minutes.
In one minute:
A does 1/10 of the work
B does 1/12 of the work
C does 1/15 of the work
The pipes operate in turns (A, B, C) for 5-minute intervals.
In 15 minutes (5+5+5), the work done is:
5*(1/10) + 5*(1/12) + 5*(1/15) = 1/2 + 5/12 + 1/3 = (6 + 5 + 4)/12 = 15/12 = 5/4 = 1.25. Which is greater than 1, so the question must be incorrect

Let’s fix the question. Since together in 4 minutes:
1/a + 1/b + 1/c = 1/4. And a = 10, b = 12, c=15
1/10 + 1/12 + 1/15 = 6/60 + 5/60 + 4/60 = 15/60 = 1/4. So the information is consistent.

Consider the cycle:
A does 5/10 = 1/2
B does 5/12
C does 5/15 = 1/3
Total done = 1/2 + 5/12 + 1/3 = (6+5+4)/12 = 15/12 = 5/4.
So they fill the tank in less than the cycle. Total work done in 1 cycle is 5/4 which is 1.25 (more than 1).
Work done in first cycle (A, B, C): 5/4. Since 1 is required, only 4/5 of the cycle is needed to complete the work. Total time is (4/5) * 15 = 12 minutes.

Cycle 1 (A,B,C) 15 min -> 5/4
We only need to complete the tank.
A does work for 5 mins = 5/10 = 1/2
B does work for 5 mins = 5/12
C does work for 5 mins = 5/15 = 1/3
In 15 min , they fill 5/4.
If they started with A -> B -> C -> A -> B -> C:
(A,B,C) -> 5/4 (15 mins)
Therefore, time to fill the tank = 4/5 * 15 = 12 minutes.
Let’s analyze.
A does 1/10 in 1 min.
B does 1/12 in 1 min.
C does 1/15 in 1 min.
Cycle 1:
A: 5/10 = 1/2
B: 5/12
C: 5/15 = 1/3
Total in 1 cycle (15 min) : 1/2 + 5/12 + 1/3 = 15/12 = 5/4. Too much.
In 1 cycle, 5/4 tank is filled. In 15 min.
Need 1 tank to be filled.
15 min fills 5/4 tanks. So, need to find the fraction * 15 = 1 tank.

Tank filled after 10 min:
A: 5/10= 1/2
B: 5/12
Remaining work: 1 – 1/2 – 5/12=1/12.
C does 1/15 in one min.
Time required = (1/12) / (1/15) = 15/12 = 5/4
So, 10 + 5/4 = 11.25 min

Correct Option: E

Q. 12 Pipe X can fill a tank in 12 hours, pipe Y can fill the same tank in 15 hours. A third pipe, Z, can empty the tank in 10 hours. If all three pipes are opened simultaneously, how long will it take to fill the tank?
Check Solution

Ans: A

Explanation: Let’s determine the work rate of each pipe. Pipe X fills 1/12 of the tank per hour. Pipe Y fills 1/15 of the tank per hour. Pipe Z empties 1/10 of the tank per hour. When all three pipes are open, the combined work rate is (1/12) + (1/15) – (1/10). To add/subtract these fractions, we need a common denominator, which is 60. So the combined work rate is (5/60) + (4/60) – (6/60) = 3/60 = 1/20. This means that with all three pipes open, 1/20 of the tank is filled per hour. Therefore, it will take 20 hours to fill the tank (the reciprocal of 1/20).

Q. 13 Two pipes fill a tank in 12 and 24 minutes. With a leak, it takes 2 minutes longer to fill the tank when both pipes are open. How long will the leak take to empty a full tank?
Check Solution

Ans: D

Explanation: Let the volume of the tank be V. Pipe 1 fills the tank in 12 minutes, so its rate is V/12. Pipe 2 fills the tank in 24 minutes, so its rate is V/24. When both pipes are open, without the leak, they fill at a combined rate of V/12 + V/24 = (2V + V)/24 = 3V/24 = V/8. The time to fill without leak is 8 minutes.

With the leak, the time taken is 12+2=14 minutes. Let the leak empty the tank in ‘x’ minutes, so the leak’s rate is V/x.

Combined rate with leak: (V/12 + V/24 – V/x) = V/14
Simplifying this to the rate: 1/12 + 1/24 – 1/x = 1/14
1/x = 1/12 + 1/24 – 1/14
1/x = (14+7-12)/168
1/x = 9/168 = 3/56
x=56/3
In the modified question:
Let the time taken to fill the tank with both pipes be T minutes.
Pipe 1 fills in 12 minutes, so rate = 1/12
Pipe 2 fills in 24 minutes, so rate = 1/24
Combined rate of both pipes = 1/12 + 1/24 = 2/24 + 1/24 = 3/24 = 1/8. So, they fill the tank in 8 minutes.

With the leak, it takes 2 minutes longer, so time = 8+2=10 minutes.
Let the leak take x minutes to empty the tank. Rate of the leak = -1/x

Combined rate with leak = 1/12 + 1/24 – 1/x = 1/10
1/x = 1/12 + 1/24 – 1/10 = 5/60 + 2.5/60 – 6/60
1/x = (5+2.5-6)/60 = 1.5/60 = 3/120 = 1/40
x=40

Considering original solution:

Without leak time is 8 minutes. With leak time = 12+2 = 14 minutes.
Let the time to empty by leak be x minutes.
Combined rate with leak = 1/12+1/24 -1/x = 1/14
1/8 + (-1/x) = 1/10. NO
1/10 = 1/12+1/24 -1/x. NO.

Let the tank capacity be LCM(12, 24) = 24 litres.

Pipe 1 fills 24/12=2 litres/min
Pipe 2 fills 24/24=1 litre/min
Both pipes fill 2+1=3 litres/min
Time to fill tank without leak: 24/3 = 8 min.
Time taken with leak: 8+2=10 minutes
Combined time of both pipes and leak to fill the tank = 10 min
Let the leak empty x litres per minute.
Then, 24/(2+1-x) = 10 minutes
24/(3-x) = 10
3-x = 24/10 = 2.4
x = 3-2.4 = 0.6 litres/min
Time taken by leak = 24/0.6 = 40 min

Correct Option: D

Q. 14 Two pipes, A and B, working together can fill a tank in 20 hours. Pipe C can empty 40% of the tank in 20 hours. How long will it take for all three pipes working together to fill 60% of the tank?
Check Solution

Ans: A

Explanation: Let the volume of the tank be V.
Pipe A and B together fill the tank in 20 hours. So, their combined rate is V/20 per hour.
Pipe C empties 40% of the tank in 20 hours. This means it empties 0.4V in 20 hours. So, the rate of pipe C is (0.4V)/20 = V/50 (emptying).
When all three pipes work together, the combined rate is (V/20) – (V/50).
Combined rate = V/20 – V/50 = (5V – 2V)/100 = 3V/100.
We want to fill 60% of the tank, which is 0.6V.
Time = (0.6V) / (3V/100) = (0.6V * 100) / (3V) = 60/3 = 20 hours.

Correct Option: A

Q. 15 Two pipes, along with a leak, fill a tank in 18 hours. If the leak is fixed after 3 hours, the pipes then take an additional 10 hours to finish filling the tank. How long would the leak take to empty a full tank on its own?
Check Solution

Ans: D

Explanation: Let the two pipes fill the tank at a combined rate of P, and the leak empties the tank at a rate of L. In the first 3 hours, the combined filling rate of pipes and the leaking rate is (P-L)*3. In the next 10 hours, only pipes are working at the rate of P, filling up the remaining part which is 10P. So, the total amount filled up equals 1 (full tank). Thus, (P-L)*3 + 10P = 1. The pipes and the leak together take 18 hours to fill the tank, so (P-L)*18 = 1. We have two equations now:
1. 3P – 3L + 10P = 1 => 13P – 3L = 1
2. 18P – 18L = 1

From equation 2, P = (1+18L)/18. Substitute this into equation 1:
13*(1+18L)/18 – 3L = 1
13 + 234L – 54L = 18
180L = 5
L = 5/180 = 1/36.
Since the leak empties the tank at a rate of 1/36 per hour, it takes 36 hours to empty the full tank alone.

From the first equation we can determine P as well: P-L = 1/18 so 13P – 3(1/36) = 1 => 13P = 1 + 1/12 = 13/12 so P=1/12.
Now check (P-L)*3 + 10P = 1: (1/12 – 1/36)3 + 10/12 = 2/36 *3 + 10/12 = 1/6 + 5/6 = 1.
And also (P-L)*18 = (1/12 – 1/36)*18 = 2/36 * 18 = 1.

Correct Option: D

Q. 16 Two workers, X and Y, can complete a task. X is twice as efficient as Y. If X takes 30 days less than Y to finish the job alone, how many days will it take them to complete the job if they work together?
Check Solution

Ans: C

Explanation: Let the number of days Y takes to complete the job be ‘d’ days. Since X is twice as efficient as Y, X takes d/2 days. Also, X takes 30 days less than Y, so d/2 = d – 30. Solving for d: d – d/2 = 30 => d/2 = 30 => d = 60 days. Therefore, Y takes 60 days and X takes 60/2 = 30 days. X’s work rate is 1/30 and Y’s work rate is 1/60. Working together, their combined work rate is 1/30 + 1/60 = 2/60 + 1/60 = 3/60 = 1/20. The number of days it takes them working together is the inverse of the combined work rate, which is 20 days.

Q. 17 X can finish a work in 36 days. Y is 33.33% more efficient than X. How many days will it take for X and Y to complete the same work together?
Check Solution

Ans: C

Explanation: Let the work done by X in one day be 1/36. Y is 33.33% more efficient than X, which means Y’s efficiency is X’s efficiency + (1/3) * X’s efficiency. So, Y’s one day work = (1/36) + (1/3)*(1/36) = (1/36) + (1/108) = (3+1)/108 = 4/108 = 1/27. When X and Y work together, their combined work in one day = 1/36 + 1/27 = (3+4)/108 = 7/108. Therefore, the number of days taken by X and Y together to complete the work = 1 / (7/108) = 108/7. Approximately equals 15.42 days, so the closest answer should be around 15, let’s recalculate and rethink the original problem to confirm: X’s efficiency = 1/36. Y is 33.33% more efficient. 33.33% can be converted into 1/3. So, Y’s efficiency = (1 + 1/3) * X’s efficiency = 4/3 * (1/36) = 1/27. Combined efficiency = 1/36 + 1/27 = (3 + 4) / 108 = 7/108. Days required working together = 1 / (7/108) = 108/7 = 15.43 days. Rounding to nearest available answer gives us 15.

Q. 18 X completes a task in 20 days. When X and Y work together, they finish the same task in 60/7 days. How much faster is Y than X at doing the work?
Check Solution

Ans: C

Explanation: Let the work done by X in one day be 1/20. Let the work done by Y in one day be 1/y. When X and Y work together, the work done in one day is 1/(60/7) = 7/60. Therefore, 1/20 + 1/y = 7/60. 1/y = 7/60 – 1/20 = 7/60 – 3/60 = 4/60 = 1/15. So, Y can complete the task in 15 days. The work done by X in a day is 1/20, and the work done by Y in a day is 1/15. Y is faster than X by (1/15 – 1/20) / (1/20) * 100% = (1/60) / (1/20) * 100% = (1/60) * 20 * 100% = (1/3) * 100% = 100/3 %.

Correct Option: C

Next Chapter: Algebra

Crack Bank Exams with LearnTheta’s AI Platform!

✅ All Topics at One Place

🤖 Adaptive Question Practice

📊 Progress and Insights

Read More

Try a smarter way to Practice? Yes No
How It Works Demo Pricing Start AI-Practice
🔥 Prepare Exams Smarter - with Adaptive Practice! ✨ Aptitude | Banking | CAT | SSC CGL | Maths | Science
Start
Scroll to Top